QC11Y guillotine type hydraulic shearing machine has two hydraulic cylinders and an accumulator. The hydraulic cylinders drive the blade carrier down. The accumulator helps to drive the blade carrier back to top dead point. The air pressure of the accumulator should be 7-8Mpa
Sometimes, the blade carrier back stroke is very slow. Evenly the blade carrier cannot return to top dead point. When this happens, operator shall inspect the accumulator air pressure and oil pressure.
This article is to introduce the nitrogen filling steps and oil filling steps.
Firstly, prepare nitrogen bottle and the nitrogen filling tool. The filling tool is normally shipped with the shearing machine.
Step 1: open the cover and the plug on the top of accumulator
Step 2: connect the filling tool with the accumulator and the nitrogen bottle
Step 3: open the valve on filling tool, then open the valve on the nitrogen bottle slowly
Step 4: close the valve on filling tool till the pressure gauge achieve at 8Mpa (refer to different model standard), close the valve on nitrogen bottle
Step 5: screw the pressure release switch on the nitrogen filling tool, till the pressure gauge back to 0
Step 6: move away the filling tool from the accumulator
To filling oil into the accumulator, it needs two persons to work together.
Step 1: one person goes to back of the shearing machine. Find the valve with pressure gauge on the bottom of the accumulator. Open the valve.
Step 2: one person goes to the front the machine. Find the oil filling button on the control panel. Keep pressing the button and ask the back person to check the oil pressure gauge.
Step 3: Once the pressure arrives at 10Mpa (refer to different model standard, 10-20Mpa), the front side person stops pressing the oil filling button. At the same time, the back side person closes the valve immediately.